Question: A project's critical path has seven tasks ( A through F ) with expected duration and standard deviations as given below. What is the critical
A project's critical path has seven tasks A through F with expected duration and standard deviations as given below. What is the critical path's expected length? What is the standard deviation of the critical paths length? Task Expected duration days Standard Deviation days A B C D E F