Question: Problem 10: A project's critical path has seven tasks (A through G) with expected durations and standard deviations as given below. a) What is the

Problem 10: A project's critical path has seven

Problem 10: A project's critical path has seven tasks (A through G) with expected durations and standard deviations as given below. a) What is the critical path's expected length? b) What is the standard deviation of the critical path's length? Task A B D Expected duration (days) Std. Dev. (days) 8 2 8 1 11 2 9 2 7 1 5 1 6 1 E F G