Question: A project's critical path has seven tasks (A through G) with expected durations and standard deviations as given below. a) What is the critical
A project's critical path has seven tasks (A through G) with expected durations and standard deviations as given below. a) What is the critical path's expected length? b) What is the standard deviation of the critical path's length? Task A B C D E F G Expected duration (days) 7 9 11 10 8 6 7 Std. Dev. (days) 2 1 2 2 1 1 1
Step by Step Solution
There are 3 Steps involved in it
Answer To find the critical paths expected length and standard deviation we need to determine the ex... View full answer