Question: A projects critical path is CDFGI. The expected time and the standard deviation of each activity are as follows. Activity A B C D E
A projects critical path is CDFGI. The expected time and the standard deviation of each activity are as follows.
| Activity | A | B | C | D | E | F | G | H | I |
| Expected Time | 2 | 5 | 8 | 6 | 4 | 9 | 10 | 1 | 5 |
| Standard Deviation | 10 | 4 | 7 | 14 | 10 | 10 | 11 | 5 | 6 |
What is the project standard deviation?
keep two decimals if not exact, either round up or down is ok. For example, for 0.1346, (0.13 or .13) and (0.14 or .14) are correct.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
