Question: A project's critical path is CDFGI. The expected time and the standard deviation of each activity are as follow table [ [ Activity ,

A project's critical path is CDFGI. The expected time and the standard deviation of each activity are as follow
\table[[Activity,A,B,C,D,E,F,G,H,I],[\table[[Expected],[Time]],2,5,8,6,4,9,10,1,5],[\table[[Standard],[Deviation]],10,4,6,14,10,10,8,5,6]]
What is the project standard deviation?