Question: Galvas Question 10 9 pts A project's critical path is CDFGI. The expected time and the standard deviation of each activity are as follows. D

Galvas Question 10 9 pts A project's critical
Galvas Question 10 9 pts A project's critical path is CDFGI. The expected time and the standard deviation of each activity are as follows. D E F G H 18 16 14 19 |10|1 15 Activity B Expected 2 15 Time Standard 10 4 Deviation 16 14 10 16 17 15 16 What is the project standard deviation? keep two decimals if not exact, either round up or down is ok. For example, for 0.1346, (0.13 or. 13) and (0.14 or. 14) are correct. Question 11 10 pts Time Estimates lin

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!