Question: A projects critical path is CEGHI. The expected finish time and the variance of each activity are as follows. Activity A B C D E

A projects critical path is CEGHI. The expected finish time and the variance of each activity are as follows. Activity A B C D E F G H I Expected FT 2 5 3 6 4 5 3 1 5 Variance 10 4 15 14 10 15 20 5 6

Question 1: What is the expected completion time of the project?

A. 15 B. 16 C. 18 D. 19 E. 24 F. 34

Question 2: What is the variance of the project?

A. 49 B. 54 C. 56 D. 59 E. 74 F. 99