Question: A project's critical path is ACDFG. The expected finish time and the variance of each activity are as follows. Activity A B C D E

A project's critical path is ACDFG. The expected finish time and the variance of each activity are as follows. Activity A B C D E F G H I Expected FT 2 5 1 6 4 3 7 1 5 Variance 10 4 15 14 10 15 20 5 6 What is the expected completion time of the project