Question: A projects critical path is ACDFG. The expected finish time and the variance of each activity are as follows. Activity A B C D E
A projects critical path is ACDFG. The expected finish time and the variance of each activity are as follows.
| Activity | A | B | C | D | E | F | G | H | I |
| Expected FT | 2 | 5 | 6 | 6 | 4 | 3 | 7 | 1 | 5 |
| Variance | 10 | 4 | 15 | 14 | 10 | 15 | 20 | 5 | 6 |
What is the expected completion time of the project?