Question: A projects precedence relationship is as follows Activity A B C D E F G H I Successor D EG F G H HI Duration
A projects precedence relationship is as follows
| Activity | A | B | C | D | E | F | G | H | I |
| Successor | D | EG | F | G | H | HI |
|
|
|
| Duration | 3 | 4 | 2 | 4 | 5 | 4 | 7 | 4 | 3 |
Draw an AOA and AON networks separately?
Use Critical path method to find the projects critical path and calculate the project duration