Question: A projects precedence relationship is as follows: Activity A B C D E F G H I Successor D EG F G H HI Duration

A projects precedence relationship is as follows:

Activity

A

B

C

D

E

F

G

H

I

Successor

D

EG

F

G

H

HI

Duration

3

4

2

4

5

4

7

4

3

  1. Draw an AOA and AON networks separately.
  2. Use Critical path method to find the projects critical path and calculate the project duration. 10points