Question: (1) A project's precedence relationship is as follows: Activity A B C D E F G H I Successor D E. G F G H

(1) A project's precedence relationship is as

(1) A project's precedence relationship is as follows: Activity A B C D E F G H I Successor D E. G F G H . Duration 3 4 2 4 5 4 7 4 3 1) Draw an AOA and AON networks separately. (10points) 2) Use Critical path method to find the project's critical path and calculate the project duration. (10points)