Question: A proposed design for a hydroelectric project is based on a discharge of 0.25 m 3 /s through the penstock and turbine (Fig. P12.50). The
A proposed design for a hydroelectric project is based on a discharge of 0.25 m 3 /s through the penstock and turbine (Fig. P12.50). The friction factor can be assumed constant, f = 0.015, and the minor losses are negligible.
(a) Determine the power in kilowatts that can be expected from the facility, assuming that the turbine efficiency is 0.85.
(b) Show that the type of machine to be installed is a Francis turbine if the desired rotational speed is 1200 rpm.
(c) Determine the size, actual speed, and actual power output of the selected turbine.
el 915 m L-350 m, D 00 mm, el 92m Fig. P12.50
Step by Step Solution
3.34 Rating (166 Votes )
There are 3 Steps involved in it
To solve this problem well need to apply fluid mechanics principles to determine the expected power output and analyze the suitability of the turbine ... View full answer
Get step-by-step solutions from verified subject matter experts