Question: A quality analyst wants to construct a sample mean chart for controlling a packaging process. He knows from past experience that when the process is

A quality analyst wants to construct a sample mean chart for controlling a packaging process. He knows from past experience that when the process is operating as intended, the packaging process has a standard deviation of one ounce. Each day last week, he randomly selected four packages and weighed each. The data from that activity appear below.

Day Package 1 Package 2 Package 3 Package 4
Monday 23 22 23 24
Tuesday 23 21 19 24
Wednesday 20 19 20 23
Thursday 18 19 20 22
Friday 18 20 22 20

1. Assume this process is In Control. Which of the following shows the Process Capability if the specifications are at 20.8 2.2?

A) 1

B) 1.33

C) 1.6

D) 1.46

E) 1.5

F) None of the above (What is your answer?)

2. Assume process standard deviation is not known and process is In Control. Which of the followings show the Process Capability if the specifications are at 21 5? A) 1

B) 1.33

C) 1.6

D) 1.46

E) 0.9

F) None of the above (What is your answer?)

3. Which of the followings show the appropriate control chart we can develop for this process?

A) P-Chart

B) Np-Chart

C) X-bar Chart

D) R Chart

E) X-bar and R Chart

F) None of the above (What is your answer?)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!