Question: A senior MIS design class project team has developed a schedule of activities for their project using their best estimate of completion times as shown
A senior MIS design class project team has developed a schedule of activities for their project using their best estimate of completion times as shown in the following table.
| Activity | Time | Immediate Predecessor |
|---|---|---|
| A. find client | 6 | |
| B. write prospectus | 3 | A |
| C. obtain approval from client and professor | 4 | B |
| D. complete programming | 13 | C |
| E. do industry background research | 11 | |
| F. write final paper | 6 | D, E |
| G. write oral report | 5 | D, E |
Both written and oral reports are required. Draw the project network. Can they complete the project in the 40 class days remaining until the end of the semester? ---Select--- Yes No , they can complete it in time since the project is expected to be completed in days.