Question: A senior MIS design class project team has developed a schedule of activities for their project using their best estimate of completion times as shown

A senior MIS design class project team has developed a schedule of activities for their project using their best estimate of completion times as shown in the following table.

Activity Time Immediate Predecessor
A. find client 6
B. write prospectus 3 A
C. obtain approval from client and professor 4 B
D. complete programming 13 C
E. do industry background research 11
F. write final paper 6 D, E
G. write oral report 5 D, E

Both written and oral reports are required. Draw the project network. Can they complete the project in the 40 class days remaining until the end of the semester? ---Select--- Yes No , they can complete it in time since the project is expected to be completed in days.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!