Question: A senior MIS design class project team has developed a schedule of activities for their project using their best estimate of completion times as shown

A senior MIS design class project team has developed a schedule of activities for their project using their best estimate of completion times as shown in the following table.
\table[[Activity,Time,Immediate Predecessor],[A. find client,5,],[B. write prospectus,3,A],[C. obtain approval from client and professor,5,B],[D. complete programming,13,C],[E. do industry background research,11,],[F. write final paper,6,D, E],[G. write oral report,5,D, E]]
Both written and ofal reports are required. Draw the project network. Can they complete the project in the 42 class days remaining until the end of the semester? , they can complete it in time since the project is expected to be completed in days.
 A senior MIS design class project team has developed a schedule

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!