Question: A senior MIS design class project team has developed a schedule of activities for their project using their best estimate of completion times as shown
A senior MIS design class project team has developed a schedule of activities for their project using their best estimate of completion times as shown in the following table.
Activity Time Immediate Predecessor
A find client
B write prospectus A
C obtain approval from client and professor B
D complete programming C
E do industry background research
F write final paper D E
G write oral report D E
Both written and oral reports are required. Draw the project network. Can they complete the project in the class days remaining until the end of the semester?
Select yes or no
they can complete it in time since the project is expected to be completed in
days.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock