Question: A service has five tasks, performed in sequence.In the instance when there is more than one worker assigned to a task, each worker performs the
A service has five tasks, performed in sequence.In the instance when there is more than one worker assigned to a task, each worker performs the entire task and they both can be working on different "items" at the same time.
Task Task time per worker # of workers
1 2 min 1
2 6 min 1
3 14 min 2
4 4 min 1
5 15 min 3
- What is the capacity (hourly) of the process as a whole?
- What is the bottleneck of the process?
- What is the throughput time (assuming no wait time)?
- Where would you expect customers to wait?