Question: A seven-activity CPM project is described by the table and Network below. The critical path for this network is A-D-G and the project completion time
A seven-activity CPM project is described by the table and Network below.

The critical path for this network is A-D-G and the project completion time is 13 days.
If a deadline of 10 days is imposed, what activities should be crashed? What is the total minimum cost that is incurred for crashing the project from 13 days to 10 days? What is the total cost to complete the project in 10 days? Show your work (9 points).