Question: Consider the following project. Marks-10 Task Immediate Predecessors Optimistic Most probable Pessimistic Crash Time Normal Cost Crash Cost A - 4 6 8 4 1000
Consider the following project. Marks-10
| Task | Immediate Predecessors | Optimistic | Most probable | Pessimistic | Crash Time | Normal Cost | Crash Cost |
| A | - | 4 | 6 | 8 | 4 | 1000 | 1900 |
| B | - | 6 | 8 | 16 | 7 | 1000 | 1800 |
| C | A, B | 2 | 4 | 6 | 2 | 1500 | 2700 |
| D | C | 8 | 10 | 24 | 8 | 2000 | 3200 |
| E | C | 7 | 10 | 13 | 7 | 5000 | 8000 |
| F | E | 4 | 6 | 8 | 4 | 3000 | 4100 |
| G | C | 4 | 6 | 20 | 5 | 8000 | 10250 |
| H | D, F, G | 4 | 6 | 8 | 4 | 5000 | 6400 |
| I | D, F | 4 | 6 | 14 | 4 | 10000 | 12400 |
| J | H | 3 | 4 | 5 | 3 | 4000 | 4400 |
| K | I, J | 2 | 4 | 6 | 3 | 5000 | 5500 |
- Draw a project network
- Find the critical path and expected project completion time.
- Assuming that management desire a 12 weeks project completion time. What activity should be crashed?
- Activity schedule table after crashing.
- Find total project cost after crashing.