Question: A simple CPM network has five activities, A , B , C , D , and E . A is an immediate predecessor of B

A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of B and of C. B is an immediate predecessor of D and of E. C is an immediate predecessor of E. Which of the following statements is TRUE?
Question 1Answer
a.
There are three paths in this network.
b.
There are four paths in this network.
c.
There are two paths in this network.
d.
There are five paths in this network.