Question: A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B is
A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor
of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate
predecessors of E. Draw the network path for this project.