Question: An activity on a PERT network has these time estimates: optimistic = 3, most likely = 5, and pessimistic = 10. Its expected time is

An activity on a PERT network has these time estimates: optimistic = 3, most likely = 5, and pessimistic = 10. Its expected time is

a. 5.33

b. 5.67

c. 5.5

d. 18

e. 5

A simple CPM network has five activities, A, B, C, D, and E.A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E.

a. There are five paths in this network.

b. There are two paths in this network.

c. There are four paths in this network

d. There are six paths in this network.

e. There are 10 paths in this network.

Please please, I don't have enough time to help me

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!