A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E. Which of the following statements is true? O A. There are six paths in this network. O B. There are 25 paths in this network OC. There are two paths in this network OD. There are four paths in this network. O E. There are five paths in this network. Click to select your