Question: A single-machine work center can process production orders with a service time of 5 hours per order on average. Within an 8-hours-shift 1.4 orders arrive

A single-machine work center can process production orders with a service time of 5 hours per order on average. Within an 8-hours-shift 1.4 orders arrive on
average. Arrivals follow a Poisson process.
What is the ratio between average service time and average flow time of a production order in the case of deterministic service times?
What is the intuition behind having substantial waiting times for a utilization clearly less than 100%?
A single-machine work center can process
A single-machine work center can process production orders with a service time of 5 hours per order on average. Within an 8 -hours-shift 1.4 orders arrive on average. Arrivals follow a Poisson process. What is the ratio between average service time and average flow time of a production order in the case of deterministic service times? What is the intuition behind having substantial waiting times for a utilization clearly less than 100\%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!