Question: A single-machine work center can process production orders with a service time of 5 hours per order on average. Within an 8-hours-shift 1.4 orders arrive
A single-machine work center can process production orders with a service time of 5 hours per order on average. Within an 8-hours-shift 1.4 orders arrive on
average. Arrivals follow a Poisson process.
What is the ratio between average service time and average flow time of a production order in the case of deterministic service times?
What is the intuition behind having substantial waiting times for a utilization clearly less than 100%?