Question: A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below. table

A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below.
\table[[IMMEDIATE,,,,],[AREDECESSOR,a,m,b,],[A TIVITY,PRED,1,7,13],[B,-,5,8,17],[C,A,8,14,20],[E,B,4,7,16]]
a) Find the expected completion cientrar this project.
The expacted completion time for the project is (ente, woy response as a whole number).
b) What variance value would be used to find probabilitios iof fing by certain time?
The project variance value of completion time is (enterseronse as a whole number).
 A small software development project at Krishna Dhir's firm has five

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!