Question: A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below. IMMEDIATE PREDECESSOR

A small software development project at Krishna
A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below. IMMEDIATE PREDECESSOR ACTIVITY A m 4 a 1 5 4 3 2 > NWU- b 7 11 10 9 2 NOVO B 2 a) Find the expected completion time for this project The expected completion time for this project is (enter your response as a whole number)