Question: A small software development project has five major activities. The times are estimated and provided in the table below. Activity Immediate Predecessor a m b

A small software development project has five major activities. The times are estimated and provided in the table below.
Activity
Immediate
Predecessor
a
m
b
A
--
2
5
8
B
--
10
10
10
C
A
4
7
10
D
B
2
5
14
E
C
3
3
3
What is the expected completion time for this project?
14
10
12
16