Question: A software development company is using Function point method to estimate the time and cost of the project. The company will assign 4 people to

A software development company is using "Function
A software development company is using "Function point method" to estimate the time and cost of the project. The company will assign 4 people to work on the project. Each person earns $650/month. Each person can do 5 function points/month. If the estimated total function point count is 310, calculate the estimated project duration (write the result in the space provided below). I 1 A B 1