Question: A software development project that you are managing has budget at completion of $410,000. At month seven, 65% of the work was planned to be
A software development project that you are managing has budget at completion of $410,000. At month seven, 65% of the work was planned to be complete but stands at 50%. Actual cost is $275,000. What is the project's ETC?