Question: A solved PERT problem is detailed in the table below. The expected time and variance values and the critical activities are given in the table
A solved PERT problem is detailed in the table below. The expected time and variance values and the critical activities are given in the table below. Answer the following questions by filling the blanks (WRITE YOUR ANSWERS TO 2 DECIMAL PLACES. DO NOT ROUND UP OR DOWN):
a. The expected project completion time for this problem is and the standard deviation is .
b. There is a 0.95 probability that the project will be completed by weeks.
| Activity | Expected time | Variance | Critical? |
| A | 10 | 0.36 | Yes |
| B | 7 | 0.11 | No |
| C | 7 | 0.25 | No |
| D | 3 | 0.48 | Yes |
| E | 5 | 1.60 | Yes |
| F | 7 | 0.69 | No |
| G | 2 | 3.69 | Yes |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts