Question: A student named Saada wants to use the CPM method to analyze a project schedule. She was able to obtain the following information. Draw the

A student named Saada wants to use the CPM method to analyze a project schedule. She was able to obtain the following information.
Draw the network diagram using the AON format (activity on node). Calculate ES/EF/LS/LF/slack for all activities.
activity Immediate predecessor(s) Duration (days)
A None 2
B A 3
C A 4
D B,C 3
E D 7
F D 3
G E,F 5