A student project team frantically worked on their final project report due in two days. The deadline loomed and they had several other things to accomplish data entry, data analysis, report writing, collating, printing, and binding. They finally figured out that they probably did not have enough toner, paper, binder or computing time available to accomplish all that they had left to do. Their project is unfortunately:
Question 44Select one:
a.
Time constrained.
b.
Resource constrained.
c.
Personally constrained.
d.
Mix-constrained.