Question: A) Study the below table and answer the questions that follow Activity Normal Crash Time Cost Time Cost 1-2 4 150 3 210 1-3 3
A) Study the below table and answer the questions that follow Activity Normal Crash Time Cost Time Cost 1-2 4 150 3 210 1-3 3 40 3 40 2-3 2 100 3 120 2-4 7 420 5 580 2-5 9 720 7 810 3-5 5 250 4 300 4-5 0 0 0 0 5-6 6 320 4 410 6-7 4 400 3 470 6-8 13 780 10 900 7-8 10 1000 9 1200 Required: 1. Draw the network for the project & Critical path 2. Calculate the cost slop of the project