Question: Question 3 The table gives information on the project schedule described in Question 2. Use it to answer the questions that follow. Activity Normal Normal

Question 3 The table gives information on the
Question 3 The table gives information on the project schedule described in Question 2. Use it to answer the questions that follow. Activity Normal Normal Crash Crash Time Cost Time Cost A 7 3,000 3 6,000 B 8 15,000 5 20,000 9 4,000 6 9,000 D 10 7,000 9 10,000 E 12 5,000 7 10.000 (a) Determine the cost to crash per day for each activity. [5 marks] (b) It is proposed that the duration of the project be crashed to 22 days. Find the new cost of executing the entire project. [12 marks]