Question: A task has an optimistic completion time of 8 days, a most likely time of 11 days, and a pessimistic time of 14 days. The

A task has an optimistic completion time of 8 days, a most likely time of 11 days, and a pessimistic time of 14 days. The expected task duration is: A. 10.5 days B. 9.5 days C. 10 days D. 11 days E. 12 days F. 11.5 days