Question: A task has an optimistic completion time of 8 days, a most likely time of 11 days, and a pessimistic time of 14 days. The

A task has an optimistic completion time of 8 days, a most likely time of 11 days, and a pessimistic time of 14 days. The expected task duration is: A. 11 days B. 10 days C. 9.5 days D. 11.5 days E. 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!