Question: A task is scheduled for 8 hours a day over 4 days. If the actual work hours you enter in the Time Phase grid are

A task is scheduled for 8 hours a day over 4 days. If the actual work hours you enter in the Time Phase grid are different than the schedule, how does Project apply this to the scheduled values? Select an answer: Project changes the scheduled values when you save the table Project changes the scheduled values when you refresh the table Project changes the schedule values after you make your last entry Project changes the scheduled values as you enter each actual value