Question: A task was timed for 60 cycles. It took an average of 1.25 minutes per cycle. The performance rating was 94 percent, and workday allowance
A task was timed for 60 cycles, it took an average of 1.25 minutes per cycle. The performance rating was 94 percent, and workday allowance is 12 percent Determine each of the following. (Do not round intermediate calculations. Round the final answers to 2 decimal places.)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
