Question: A task was timed for 60 cycles. It took an average of 1.45 minutes per cycle. The performance rating was 80 percent, and workday allowance
A task was timed for 60 cycles. It took an average of 1.45 minutes per cycle. The performance rating was 80 percent, and workday allowance is 14 percent. Determine each of the following. (Do not round intermediate calculations. Round the final answers to 2 decimal places.)
| a. | Observed time. | ______minutes |
| b. | Normal time. | ______minutes |
| c. | Standard time. | _______minutes |