Question: A task was timed for 60 cycles. It took an average of 1.25 minutes per cycle. The performance rating was 94 percent, and workday allowance
A task was timed for 60 cycles it took an average of 125 minutes per cycle. The performance rating was 94 percent, and workday allowance is 12 percent. Defermine esch of the following (Do not round imermediate caleulations, Round the finnt onswors to 2 decimal plnces.)