Question: A team has just outlined its approach to a problem. Part of its plan is to have the team members' manager closely monitor the daily
A team has just outlined its approach to a problem. Part of its plan is to have the team members' manager closely monitor the daily tasks. The manager should discourage this approach and remind the team the project is its responsibility, but he is available for assistance.