Question: A technical team can begin to edit a large document 1 5 days after it begins writing it . What kind of dependency would this

A technical team can begin to edit a large document 15 days after it begins writing it. What kind of dependency would this represent?
Question 1 options:
Finish-to-start with a 15-day lag
Finish-to-finish with a 15-day lead
Start-to-start with a 15-day lag
Start-to-start with a 15-day lead