Question: A technical team can begin to edit a large document 15 days after it begins writing it. What kind of dependency would this represent? Start-to-start
A technical team can begin to edit a large document 15 days after it begins writing it. What kind of dependency would this represent?
Start-to-start with a 15-day lead Finish-to-finish with a 15-day lead Start-to-start with a 15-day lag Finish-to-start with a 15-day lag