Question: A test engineer is to conduct environmental testing but the chamber cannot hold all the equipment that needs to be tested. This is an example

 A test engineer is to conduct environmental testing but the chamber

A test engineer is to conduct environmental testing but the chamber cannot hold all the equipment that needs to be tested. This is an example of a constraint that could impact the sequence and timing of activities in a project network. What type of constraint is it? Select one: a. Physical b. Time c. Resource d. Scheduling e. Technical