Question: A test engineer is to conduct environmental testing but the chamber cannot hold all the equipment that needs to be tested. This is an example
A test engineer is to conduct environmental testing but the chamber cannot hold all the equipment that needs to be tested. This is an example of a constraint that could impact the sequence and timing of activities in a project network. What type of constraint is it? a. Physical b. Technical c. Resource d. Scheduling e. Time
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts