Question: a) The expected (estimated) time for activity C is enter your response here weeks. (Round your response to two decimal places.) b) The variance for
a) The expected (estimated) time for activity C is enter your response here weeks. (Round your response to two decimal places.)
b) The variance for activity c is ___ weeks
c) based on calculation of the estimated times, the critical path is:
d) the activity variance along with the critical path is ____ weeks
e) Using the standard normal table, the probability that hopkins hospitality will finish the project in 36 weeks or less is:
Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motelsStep by Step Solution