Question: a) Using the FCFS (first come, first served ) decision rule for sequencing the jobs, the order is (assume that jobs came in the order

a) Using the FCFS (first come, first served )

a) Using the FCFS (first come, first served ) decision rule for sequencing the jobs, the order is (assume that jobs came in the order in which they are listed in the table):

The average tardiness (job lateness) for the sequence developed using the FCFS rule = ___ days (round your response to two decimal places).

The percentage utilization for the sequence developed using the FCFS rule = ___%(enter your response as a percentage rounded to two decimal places).

b) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received):

The average tardiness (job lateness) for the sequence developed using the EDD rule = ____ days (round your response to two decimal places).

The percentage utilization for the sequence developed using the EDD rule = ____%(enter your response as a percentage rounded to two decimal places).

c) Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received):

The average tardiness (job lateness) for the sequence developed using the SPT rule = ___ days (round your response to two decimal places).

The percentage utilization for the sequence developed using the SPT rule = ____%(enter your response as a percentage rounded to two decimal places).

d) Using the LPT (longest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received):

The average tardiness (job lateness) for the sequence developed using the LPT rule = ___ days (round your response to two decimal places).

The percentage utilization for the sequence developed using the LPT rule = ___ %(enter your response as a percentage rounded to two decimal places).

a) Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: The following jobs are waiting to be processed at Julie Morel's machine center: Sequence Job 1 A Job A N D B C Date Job Received 115 122 120 118 125 Due Date 185 195 180 200 205 Duration (days) 17 20 14 22 3 D 4 B E 16 5 E All dates are according to shop calendar days. Today on the planning calendar is day 130, and none of the jobs have been started or scheduled. Compute all times based on initiating work on day 130. The total flow time for the sequence developed using the FCFS rule = |days (round your response to two decimal places)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

1 Data Provided Job Date Received Due Date Duration days A 115 185 17 B 122 195 20 C 120 180 14 D 118 200 22 E 125 205 16 Definitions Part a FCFS Firs... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!