Question: a. Using the project network that follows in the attachment, complete the forward and backward pass, activity slack and identify the critical path, for a

a. Using the project network that follows in the attachment, complete the forward and backward pass, activity slack and identify the critical path, for a group term paper.
b. Use this information to create a Gantt chart for the project and be sure to show slack for noncritical activities.
D Group Term Paper Edit paper 2 A E G H Identify topic Research topic 5 Draft paper Create graphics Proof Submit Paper 1 3 1 1 1 F Legend References ES ID EF 1 SL Description LS DUR LF Identify topic Research topic Draft paper Edit paper Create graphics References Proof Final Draft 0 2 4 6 8 10 12 14Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts