Question: A valid master production schedule (MPS) has been created to support anticipated forecast demand, actual customer orders and inventory goafs. Which of the following best
A valid master production schedule (MPS) has been created to support anticipated forecast demand, actual customer orders and inventory goafs. Which of the following best describes how material requirements planning fMRP) will use this information? A. The MPS and bills of material (BOM) will be used to determine the gross requirements for dependent items. B, The computed available-to-promise (ATP) information will be used to determine the fead time of finished goods deliveries, C. The net requirements in the MPS will be used to determine the net requirements for a!! needed component parts. D, MRP will create scheduled receipts to align with the MPS and ensure adequate finished goods availability